ANALISIS AKURASI QTO PEKERJAAN PERKERASAN JALAN BERBASIS BIM PADA PROYEK BRT JALUR PANGLIMA DENAI – SISINGAMANGARAJA
Accuracy Analysis of Bim-Based Quantity Take-Off (QTO) for Road Pavement Works on The Bus Rapid Transit (BRT) Panglima Denai – Sisingamangaraja Corridor
DOI:
https://doi.org/10.59003/nhj.v6i5.2356Keywords:
Building Information Modeling, Civil 3D, Quantity Take-Off, road pavementAbstract
Road pavement works in the BRT Metropolitan Mebidang Construction Project involve a high level of complexity due to the use of a dedicated corridor that repeatedly accommodates heavy vehicle loads. Therefore, accurate Quantity Take-Off (QTO) calculations are critical. Conventional QTO methods, which are performed manually using AutoCAD and Microsoft Excel, are prone to human error and require relatively long processing times. This study aims to calculate the volume of road pavement works using a Building Information Modeling (BIM)-based method with Autodesk Civil 3D and to determine the level of accuracy and deviation compared with the conventional method in the BRT Metropolitan Mebidang Project, specifically the Panglima Denai–Sisingamangaraja section, which has a length of 7.39 km. This study employed a quantitative approach with a case study design. The research stages included modeling the alignment, profile, and pavement cross-section assembly based on the Detail Engineering Design (DED), developing a 3D corridor model, and calculating material volumes using the Compute Materials feature. The resulting volumes were then compared with the project’s Bill of Quantity (BOQ) data. The results showed that the BIM-based pavement volumes were 1,396 m³ of AC-WC, 4,647 m³ of K400 concrete, 2,381 m³ of K125 concrete, and 2,420 m³ of graded aggregate. The deviation of each item from the BOQ was below the tolerance limit of 5%, namely 2.31% for AC-WC, 0.30% for K400 concrete, 2.15% for K125 concrete, and 3.82% for graded aggregate, with an overall volume deviation of 1.11% (BIM: 10,055 m³ vs. conventional: 9,944 m³). These findings indicate that the BIM-based method using Autodesk Civil 3D is valid and feasible as an alternative to conventional methods for QTO calculation of road pavement works in the BRT project and could serve as a basis for standardizing BIM-based QTO in similar projects.
Downloads
References
Alifudin, R., & Mimayani. (2024). Pengaruh Implementasi BIM Terhadap Akurasi dan Waktu Perhitungan Volume Tanah pada Proyek Infrastruktur. Seminar Nasional Sains dan Teknologi Terapan XII.
Asih, W. R., Bayzoni, Husni, H. R., & Niken, C. (2022). Perbandingan Quantity Take Off (QTO) Material Berbasis Building Information Modeling (BIM) Terhadap Metode Konvensional pada Struktur Pelat. JRSDD, 10 (4): 563-574.
Cucuzza, M., & Vanossi, A. (2022). BIM Dimensions: From 3D To 7D. Milan: Politecnico Di Milano.
Febriansyah, F. S. (2021). Implementasi Bimpada Proyek Jalan Tol Pasuruan-Probolinggo Seksi 4 Untuk Perhitungan Quantity Take-Off Timbunan. AGREGAT, 5 (2).
Ferial, R., Hidayat, B., Pesela, R. C., & Daoed, D. (2021). Quantity Take-Off Berbasis Building Information Modeling (Bim) Studi Kasus: Gedung Bappeda Padang. Jurnal Rekayasa Sipil, 17 (3).
Handayani, A. T., Budiman, E., & Rahman, T. (2024). Penerapan Building Information Modelling (BIM) Dalam Menghitung Quantity Take Off Material Struktur. Jurnal Teknologi Sipil. Jurnal Ilmu Pengetahuan Dan Teknologi Sipil, 8.
Kementerian Pekerjaan Umum Dan Perumahan Rakyat Direktorat Jenderal Bina Marga. (2024). Manual Desain Perkerasan Jalan No. 03/M/BM/2024. Jakarta.
Kementrian Pekerjaan Umum Dan Perumahan Rakyat Direktorat Jenderal Bina Marga. (2023). Pedoman Implementasi Building Information Modelling (BIM) Pada Lingkup Pekerjaan Konstruksi Jalan Dan Jembatan. Jakarta.
Kementerian PUPR. (2023). Laporan Kinerja Kementerian PUPR 2023. Jakarta.
Purnomo, H. (2022). Hambatan Implementasi Bim Pada Proyek Konstruksi Di Indonesia. Jurnal Teknik Sipil, 18.
Rugas, Z., Waluyo, R., & Purwantoro, A. (2024). Analisis Quantity Take Off Menggunakan Building Information ModelingPada Pekerjaan Struktur Gedung Poltekkes Palangka Raya. Jurnal Saintis, 24 (01).
Sadad, I., & Niviantoro, D. (2024). Implementasi Building Information Modeling (BIM) Menggunakan Metode Quantity Take Off Untuk Menentukan Volume Pekerjaan Struktur. Jurnal Teknika Sains, 09 (02).
Stefanus, & Lutfiansyah, Y. (2025). Analisis Perbandingan Perhitungan Quantity Take-Off Metode Konvensional dengan Perhitungan Berbasis BIM Pada Pekerjaan Struktur Beton Jembatan (Studi kasus: Proyek Jalan Tol Trans Sumatera Ruas Rengat-Pekanbaru). 21 (2).
Syawaludinsyah, M. H., & Susilo, H. (2026). Evaluasi Kerusakan Perkerasan Jalan Pada Ruas Jalan Rambipuji-Balung Kabupaten Jember. Jurnal Online Skripsi Manajemen Rekayasa Konstruksipolinema, 7 (1).
Travis, J. (2021). BIM-Based Quantity Takeoff vs. Conventional Methods: A Comparative Study. Journal of Construction Engineering, 12.
Wiranti, F., Nisumanti, S., & Al Qubro, K. (2022). Analisis Perhitungan Quantity Take-Off Menggunakan Building Information Modeling (BIM) Pada Proyek Jalan Tol Indralaya-Prabumulih. Jurnal Rekayasa, 12 (02): 192-202.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Izdihar Fairuz Hadi

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
NHJ is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Articles in this journal are Open Access articles published under the Creative Commons CC BY-NC-SA License This license permits use, distribution and reproduction in any medium for non-commercial purposes only, provided the original work and source is properly cited.
Any derivative of the original must be distributed under the same license as the original.